Since the boat arrived on 22nd January 2006, much of the rest of the year involved cutting out of badly rusted parts and descaling the hull as much as possible. Many unwanted bits were taken out as well including a vast array of heavy walled pipe that went into the bottom of the keel and off to flanges designed for pumps and valves. Whoever put these in originally obviously didn't understand that these area of the keel would hold ballast and any bilge pumping would be above this ballast.
A bit of a Chronological list follows of other work that has happened between Kaipuke's arrival and now.
30th September 2006 - Sold Cavalli, our Cavalier 32 yacht.
1st October 2006 - Purchased Nissan MD92 9.2 litre diesel engine & ZF320 gearbox.
November 2006 - Removed surplus equipment from engine e.g. Power Steering pump, and compressor for air brakes.
January 2007 - Purchased cobination welder/plasma cutter. Saved heaps of hours.
March/April 2007 - Major hull repairs completed. About 1/3 of the plate under the waterline was replaced.
May 2007 - KAipuke goes by truck to Bay Blasting and Engineering for sand blast and prime, then returns to Russell.
22nd June 2007 - Have decide to ballast with Steel Punchings and resin. Four drums of punchings arrive Metal Skills Ltd. in East Tamaki, Auckland.
June 2007 - The glass goes in to the Main cabin.
rest of 2007 - Mainly painting the interior with stripe coat and undercoats.
11th December 2007 - Gell coat polyester resin arrives for ballast.
December 2007/January 2008 - Install ballast.
January 2008 - Purchased PRM750 gearbox. The original ZF gearbox was so huge that it wasn't going to fit into the keel area.
31st January 2008 - Two more drums of punchings arrive as the original estimate of weight per drum was over stated.
May 2008 - Made "chimneys" for engine room air vents.
June 2008 - Framed up forward cabin bulkheads, and clad in plywood. These will be clad in rimu later.
July/August 2008 - Fit out forward cabin, including workbench and single bunk.
October 2008 - Engineering work to marinise the Nissan engine almost complete, including water cooled exhaust manifold.